The work: Extending the reinforced concrete channel walls away from Weymoor Bridge, extending the walls constructed in 2024. Tasks include building and installing formwork, reinforcement, and casting the concrete. The same mix of timber shutters and system shutters as used in 2024 will be used again. If the concrete walls progress well then the camps may also make a start on the inner towpath wall, which will be built in concrete blockwork.
The reason: Last year’s Camps diverted the existing stream through a new culvert crossing underneath the canal. A reinforced concrete channel is required to form the walls and base of the canal as it narrows and passes under the bridge and over the top of the culvert.
The restoration: Cotswold Canals Trust aims to reopen the route from the Thames at Inglesham to the Gloucester & Sharpness Canal at Saul, with a phased approach. Phase 1a from Stonehouse to Brimscombe is largely complete; work is in hand on Phase 1b to re-connect this to the canal system at Saul. Phase 2 will restore the eastern end from Inglesham to the Cotswold Water Park (including Weymoor Bridge). Finally, Phase 3 will tackle the difficult central section from the Water Park to Brimscombe.
The work: Extending the reinforced concrete channel walls away from Weymoor Bridge, extending the walls constructed in 2024. Tasks include building and installing formwork, reinforcement, and casting the concrete. The same mix of timber shutters and system shutters as used in 2024 will be used again. If the concrete walls progress well then the camps may also make a start on the inner towpath wall, which will be built in concrete blockwork.
The reason: Last year’s Camps diverted the existing stream through a new culvert crossing underneath the canal. A reinforced concrete channel is required to form the walls and base of the canal as it narrows and passes under the bridge and over the top of the culvert.
The restoration: Cotswold Canals Trust aims to reopen the route from the Thames at Inglesham to the Gloucester & Sharpness Canal at Saul, with a phased approach. Phase 1a from Stonehouse to Brimscombe is largely complete; work is in hand on Phase 1b to re-connect this to the canal system at Saul. Phase 2 will restore the eastern end from Inglesham to the Cotswold Water Park (including Weymoor Bridge). Finally, Phase 3 will tackle the difficult central section from the Water Park to Brimscombe.
£80 for the 7-day Canal Camp